Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
checklist, check, list-3944447.jpg

Pre-Qualification – for Construction Contracts

Posted on May 15, 2023May 15, 2023

Construction contracts are normally awarded to a qualified bidder who is having:

– Appropriate capabilities; and

– Other resources.

This can be achieved in two ways:

a) To verify whether the selected bidder possesses the required qualifications and experience before the contract award (post qualification);

b) To ensure that bids are submitted only by firms that have the necessary qualifications and experience (pre-qualification).

Hence Purpose of Pre-qualification is:

To ensure that bids are submitted only by firms, or a group of firms possess the necessary qualification in terms of:

a) Experience and past performance,

b) Financial capacity; and

c) Technical capability concerning personnel, equipment, and plant.

Prequalification is generally used for;

Large or complex civil works;

Design and Build or Turnkey contracts;

Supply and installation of expensive or technically complex industrial plant/equipment.

Advantages of pre-qualification:

For insufficiently qualified bidders;

  • Avoid the expense of bidding;
  • Encourage to form joint ventures.

For clients

  • Protect from unqualified bidders;
  • Indicate the number of firms interested in bidding;
  • Reduces the amount of work/time involved in evaluating bids from unqualified bidders; 
  • Assess the eligibility for domestic preference.

For qualified bidders;

  • Encourages reputable contractors to bid;
  • Encourage them to price their bids with the awareness that they are competing against other qualified bidders;
  • Assures the bid will not be rejected on qualification grounds.

Disadvantages of pre-qualification:

  • Increase procurement lead time;
  • The client is required to review all prequalification applications;
  • Collusion is easier among a limited number of bidders.

Pre-qualification Process;

  • Advertisement;
  • Issue of Pre-qualification Questionnaire;
  • Receipt of pre-qualification applications;
  • Evaluation of applications;
  • Inviting all firms found capable of performing the contract to submit bids.

Evaluation of prequalification applications:

  • Criteria comprise establishing whether the applicant has adequate:
  • Financial capacity;
  • Technical capacity;
  • Relevant experience.

Methods of Evaluation

Two methods are widely practiced:

a) Scoring system:

b) Pass/fail criteria.

Scoring system:

Major features:

Establishment of groups and assignment of the minimum score;

  • Assignment of sub-criteria to each group.
  • Usually 3 groups;
  •  Financial capability;
  • Technical qualifications (management, staff, and equipment);
  • Experience (including past performance).

Pass/fail criteria:

Major features:

Pre-qualification will be based on applicants meeting all the minimum pass-fail criteria of the predefined factors given in the prequalification document.

Factors considered:

  • General construction experience;
  • Financial position;
  • Personnel and equipment capabilities.

Pre-Qualification Document

The pre-qualification document generally consists of:

a) Invitation for pre-qualification;

b) Instructions to applicants;

c) Letter of application; and

d) Standard forms to submit information.

1 thought on “Pre-Qualification – for Construction Contracts”

  1. AHANGA AMBROSE HANS says:
    October 24, 2023 at 6:40 pm

    What key elements do you look out for during post qualification of high rise buildings

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes