Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
heavy machine, excavator, construction-3088700.jpg

Techniques used to control groundwater

Posted on August 29, 2021August 30, 2021

Water held in soil is termed groundwater. It may be in saturated or unsaturated form. 

The water table is the line showing the change of water level in the soil. Below the water table, the soil is saturated with water. 

Water held in the soil acts as a lubricant. It increases the tendency of soil to slip or slide. This property is dangerous and causes difficulties when excavations to be done during construction works.

Construction of foundation below the subsoil water level creates problems due to waterlogging. Therefore, it is necessary to dewater the area of excavation and keep it dry.

Several operations have to be carried out within the excavation. For example, laying bed concrete, laying of RCC raft slab, construction of masonry works are a few of them. Work can be carried out efficiently when the excavation area is kept dry.

Reducing Water Level below the Excavation Bottom

For keeping the area of excavation in dry condition, the water table should be maintained at least 0.5 m below the bottom of the excavation. 

The following two methods are frequently used for lowering the water table during construction. 

Dewatering for Shallow Foundations

The simplest and easiest method is to excavate drains along the edges of the excavation, collect water to sumps and remove using pumps. This method is suitable for fairly dense soil and shallow excavations. This is an economical method and is possible of being performed with unskilled labour and simple equipment.

Dewatering for Large Excavations and Deep Foundations

Wellpoint system

Wellpoint systems are used when dewatering to be done in large excavations such as for raft foundations. In this method, the flow of groundwater into the excavation is cut off using pipe wells driven deeper than the excavation around the perimeter.

A wellpoint comprises a 120 cm long and 4 cm diameter perforated pipe, with a valve which is used to regulate the flow and a screen preventing entry of mud, etc.

These wellpoints are installed along the outside edges of the excavation at the required depth, normally deeper than the bottom level of excavation. The spacing of the wellpoint is to be decided on the type of soil, normally around 1 meter.

The wellpoint tube is connected to a pipe known as riser pipe having 5 to 7.5 cm. These are sunk into the ground by jetting. Then, these riser pipes are connected to a header pipe which is connected to a high capacity suction pump. 

The groundwater is drawn out by the operation of the pump and is discharged away from the excavation area.

When installing well points using the process of jetting, water is forced down through the wellpoint at the rate of 20 to 25 liters per second. The high-pressure water jet displaces the surrounding soil, enabling the well point to be sunk to the required depth. 

After the wellpoint has been driven into the required depth, the water jet is allowed to run for some time. It ensures washing all sand or silt out of the hole, till the return water from the hole is clean. Then, the water jet is stopped and the annular space formed around the wellpoint due to the jetting action of water is filled with coarse sand and gravel. It forms a filter zone around the wellpoint. Entering of fine particles from the surrounding soil into the wellpoint is prevented due to the filter zone. And also it prevents clogging of the wellpoint screen. Normally, the filter sand should be filled up to the water table. The depth of the hole above the water table up to the ground level can be filled with tamped clay. This acts as a clay seal reducing air getting into the wellpoint through the sand filter.

After installing and connecting all the wellpoint, the suction pump is operated. 

Due to the suction, the ball valve in the wellpoint gets closed; the groundwater is drawn in through the wellpoint screen and is sucked up through the riser pipes, flows through the header pipe, and is discharged away from the excavation area.

This method can be successfully adopted for a modest depth of excavation, normally up to 18 m. 

However, the suction pump is normally not used to lift water above 6 m depth. Therefore, in deep excavations, a multi-stage system of wellpoint can be used.  

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes