Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
building, construction, site

Unit Rate in a Bill of Quantity

Posted on October 26, 2020January 14, 2021

A unit rate may be defined as the total overall cost of a specific item description for a quantity of one unit in the bill of quantity.

This one unit shall be measured according to the S.M.M. applicable.

The unit rate must include the cost of all labor, material, plant, and main contractor’s subcontractor fee, overheads, and main contractor’s profit.

It follows that the costs of the preliminaries are priced separately from the unit rates in the bills of quantities.

Labor rates

Labor rates include – Wages, extra payments such as allowances, overtime, and holiday payments, traveling and lodging charges, bonuses, etc.

Material rates

Materials – the basic price of materials must include the cost at delivery to site, percentage allowance for all waste, unloading, storing, removing to position, including hoisting or lowering, etc.

Shrinkage and consolidation are allowed for by a percentage addition, either to the quantities of the materials or the price of the material.

Prime cost

Prime cost – when services are not executed by the builder but by the nominated sub-contractors they are included as prime cost sums. Similarly nominated suppliers’ commodities are covered by P.C. sums.

The builder is allowed profit and attendance on the prime cost sums.

Provisional Sums

Provisional Sums – when certain building works cannot be accurately measured, a provisional sum is provided in the bill of quantities to meet the charges. Examples are the breaking of an existing foundation, insurance, etc.

Overheads

It can be divided into two types – Site and General Overheads. Some examples are director’s fee, bank charges, overdraft expenses and loss of interest, office rent, taxes, cost of office staff, cost of storage of materials, deprecation of plant and office equipment, transport and traveling expenses, branch office expenses, insurance, telephone, postage, lighting, etc.

Preliminary items

The following basic preliminary items are normally considered for pricing – site supervision, temporary offices, storage sheds, small plants, concreting plants and hoists, cranes and passenger lifts, scaffolding, safety measures, welfare conditions, telephone, temporary roads, temporary fencing, setting out, watching and lighting, notices and fees to local authorities, maintenance of public and private roads, testing materials, temporary water and electricity for works, insurance, etc.

7 thoughts on “Unit Rate in a Bill of Quantity”

  1. Patrick Chauya says:
    June 3, 2023 at 12:08 pm

    it help to understand the construction concept

    Reply
  2. Samuel Taiwo Olaide says:
    October 28, 2023 at 11:15 pm

    The topic quite educative and practically incisive.. Keep it up

    Reply
  3. Akampa Clinton says:
    April 15, 2024 at 10:21 pm

    Very educative coz it explains each needful step in a very understandable way… Keep it up

    Reply
    1. ranjith1kn says:
      April 18, 2024 at 10:27 pm

      Thank you very much! Do you have any other topics which I should write about?

      Reply
    2. ranjith1kn says:
      June 9, 2024 at 11:09 am

      Thank you very much

      Reply
  4. Anthony Wiho says:
    June 8, 2024 at 5:46 pm

    Show me real examples in Civil engineering works like bailey bridge construction., roads etc

    Reply
    1. ranjith1kn says:
      June 9, 2024 at 8:17 pm

      Hi,
      I will create a post and share with you soon

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes