Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
business, signature, contract-962355.jpg

Law of contract – The Necessity of the Law

Posted on September 5, 2021September 6, 2021

Why do we need Contract Law?

It is because our promises should be binding. The law enforces certain types of promises to be binding, especially if there are some forms of exchange.

If you do not give anything back in a promise, it is called a gratuitous promise. It is not usually enforceable in law. However, if it is put in the formal document called a deed, it is an exception. 

In the kind of society we live in at present, we make lots of promises which involve exchange. For example, we buy and sell freely, on small scales as well as larger scales. We engage in the construction of larger projects like the construction of railway lines or multi-storied buildings. 

However, it is impossible to run a society if promises are not binding. For example, what happens when you order something from a manufacturer and withdraw the order when they are ready to deliver? What happens if the client refuses to pay the contractor after the construction is over? 

So, society will run smoothly if the members of the society can rely on promises made to them. The contract law looks after whether the parties to the contract fulfill their contractual promises. If one party defaults, the law tries to compensate the innocent party financially, attempting to put them in the position they would have been in if the contract had been performed as agreed. So, any party who fails to fulfill their obligations cannot simply go away with their breach.   

Contract law tries to enforce obligations which the parties have voluntarily assumed. 

However, all contracts do not have to be in writing. Even when they are in written form, important points may be left out. Therefore, it is important to find out what the parties agreed. 

This was explained in Smith v Hughes (1871).

Smith v Hughes (1871)

In this case, the complainant, Mr. Smith, was a farmer. The defendant, Mr. Hughes, was a racehorse trainer. Mr. Smith brought Mr. Hughes a sample of his oats. After seeing the sample, Mr. Hughes ordered 40-50 quarters of oats from Mr. Smith. The price was 34 shillings per quarter. 

Accordingly, to begin with, 16 quarters of oats were sent to Mr. Hughes. When it arrived, Mr. Hughes said that the oats were not the quality what he had thought they were. Since he was a racehorse trainer, he needed old oats. Mr. Hughes said old oats are the type of oats the horses had for their diet. The oats that were brought by Mr. Smith were green. But, it was the same type as the initial sample. However, Mr. Hughes refused to pay Mr. Smith for the delivery and the remaining order.

Mr. Smith argued that Mr. Hughes had breached the terms of the contract as he had not paid for the delivery and future oats to be delivered. 

The issue, in this case, was whether the contract could be avoided by Mr. Hughes, as Mr. Smith had not delivered the type of oats he had expected.

It was held that there was a legally acceptable contract between Mr. Smith and Mr. Hughes. Therefore, it would not be avoided. However, there had been no discussion between the parties regarding the delivery of old oats. An objective test revealed that a reasonable person would expect the sale of good quality oats in a similar contract since there was no express discussion of old oats. The sample submitted by Mr. Smith gave Mr. Hughes the chance to inspect the oats. 

This is an example of caveat emptor (buyer beware).

‘If, whatever a man’s real intention maybe, he so conducts himself that a reasonable man would believe he was assenting to the terms proposed by the other party, and that another party upon that belief enters into the contract with him, the man thus conducting himself would be equally bound as if he had intended to agree to the other party’s terms.’

In some cases, the basis for this approach is obvious. When you get into a hiring car and tell your destination, it is sensible for the driver to think you are agreeing to pay for the trip. It is not right to tell at the end of the trip that you had no such intention as to pay in your mind, and so you are not obliged to pay. It is true even your behavior might have suggested that.

L’Estrange v F Graucob Ltd (1934)

In this case, it was affirmed that the clauses of a written contract are binding on the signatories, even where a party is unaware of the contract’s full contents.

The claimant, L’Estrange, contracted with the defendant, Graucob to purchase a slot machine for cigarettes. 

There was an express clause in the agreement which stated;

“This agreement contains all the terms and conditions under which I agree to purchase the machine specified above and any express or implied condition, statement, or warranty, statutory or otherwise not stated herein is hereby excluded”. 

However, when put in to use after the purchase, the machine was found to be faulty. As a result, the claimant brought an action against the defendant. The claimant alleged that the machine breached the Sale of Goods Act by not being of merchantable quality. 

The defendant emphasized that the statute was made irrelevant by the inclusion of the express clause mentioned above. Therefore, he was not in breach of the agreement between the parties. The claimant responded saying she had been unaware of the clause because she had not properly read the agreement and therefore it should not apply.

The issue here was whether the clause which excluded all terms not stated in the contract should be deemed effective and binding.

The Court of Appeal determined that the express provisions of the contract were binding. It effectively excluded the relevance of statutory sales provisions. Besides, the fact that the claimant had not properly read the contract did not impact its validity. When signing the contract she consented to be bound by its contents. 

This case emphasizes the Court’s respect for the sanctity of contract.

When a person signs a contractual document, he is bound by it, even though he may not have understood or even read it.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes