Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
Quality of mixing water for Concrete

Estimating Activity cost

Posted on June 20, 2021June 20, 2021

Estimating the cost of any work items includes estimating the cost of labor, equipment, and material. The analysis of a given job requires an in-depth examination of the plans and specifications given with the bid documents, an evaluation of the soil investigation report, etc. Also, it is important to carry out a visit to the proposed site before estimating. 

For earthwork estimates, the soil report and relevant geotechnical information about the soil and other subsurface conditions are usually given with the bid documents. However, the estimator or the quantity surveyor can use other sources which may be useful in developing an accurate estimate.

Swell and compaction factors

It is important to know the physical properties of soil for accurate estimation involving the cost of excavating and hauling earth. It is because of the change of volume such as swelling of soil during the construction operations. 

During an earthwork operation, the soil is excavated from its natural state. Then, it is placed in a hauling unit and transported to the disposal area, where it is distributed and compacted. For example, 01 m3 of soil that is excavated from the ground may occupy 1.25 m3 after it is loosened and placed in the hauling unit. After the soil is compacted in place it may occupy 0.9 m3. 

The soil to be excavated, in its undisturbed condition, is called bank measure. Similarly, after being compacted in place, the volume of the filled embankment or the pit is called the bank measure. Also, any additional requirements such as excavation supports should be added to the cost estimation of an excavation operation.

Calculating truck requirements

In excavation operations, the estimator or the quantity surveyor has to decide the optimum number of trucks required to transport excavated materials. 

A simple formula can be used for these calculations based on the idea that it is desirable to have sufficient trucking capacity to ensure that the excavation equipment can operate continuously without having idling time waiting for trucks. 

For example, 03 trucks will be required if it takes 10 minutes to load a truck and 20 minutes for that truck to unload and return for another load. Then, when the first truck is away, the two other trucks can be loaded.

Therefore, the number of trucks required can be calculated as;

The number of trucks obtained from Eq. 1 should always be rounded up, no matter how small the decimal. It is better to have more rather than fewer trucks so that the excavator is always kept occupied.

Waste factors

When estimating the material required for any work item, it is necessary to add a portion as the wastage of material used. 

The quantities of material taken off are the unadjusted net amounts calculated from the drawings. Allowance for waste and spillage of this material can be made by increasing the take-off quantities or by increasing the price by a percentage factor considered reasonable. 

The values of waste factors usually lie between 01 and 10 percent for different materials.

Example – Calculate the equipment and labor prices per m3 to excavate 3,000 m3 of a trench using 0.75 m3 backhoe costing LKR  6,700/day (day = 8 hrs), plus LKR 40,000 for transportation and set up charges. The expected output is 60 m3/hr with an operator and 0.5 labor at wages of LKR 400/hr and LKR 300/hr, respectively.

Solution:

Example – Calculate the price of obtaining gravel from a pit located 16km from the work site, where the unit price is LKR 25/m3, using a loader with a rate of 50m3/hr (bank measure) and 12m3 trucks to transport the gravel. The hire charges for the loader and trucks are LKR 4,500/day and LKR 3,000/day respectively. The labor crew consists of one equipment operator at LKR 400/hr, two laborers at LKR 300/hr, and a truck driver at LKR 350/hr. The average speed of the dump is 20km/hr. The swell factor for gravel is 12%. Offloading time for trucks are 5 minutes.

Solution:

First calculating the required number of trucks to have a balanced crew;

Secondly calculating the gravel supply price;

Example – It is required to determine the unit price for mass concrete given the following information:

Mass concrete quantity = 1,080 m3.

01 m3 of mass concrete comprises 250 kg cement; 0.55 m3 of sand (fine aggregate) and 1.02 m3 of 37.5 mm metal (coarse aggregates).

The prices of the materials are LKR 22,000/M.ton; LKR 7,500/m3 and LKR 3,500/m3 for cement, sand, and 37.5 mm metal respectively. Assume 10% wastage for all materials. The details of the crew used are shown in the table below. Assume overheads and markup 20%.

Crew itemNumber employedProduction rateUnit rates
Concrete pump130 m3/hrLKR 1,500/hr
Concrete mixer39 m3/hr/machineLKR 1,000/hr/machine
Vibrator2–LKR 300/hr/one
Labour5–LKR 300/hr/person
Foreman1–LKR 400/hr/person

Solution;

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes