Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures

Latent Defects and Patent Defects in Construction

Posted on July 5, 2024July 5, 2024

Defects are features of the works that are not in conformity with the contract. Defects can be ‘patent’ or ‘latent’:

Patent defects are those that can be exposed by reasonable inspection.

Latent defects are those that cannot be exposed by reasonable inspection.

For example, problems with foundations which may not become apparent for several years after the completion come under latent defects. It can only be discovered when settlement causes cracking in the building.

After a latent defect becomes visible, it becomes patent rather than latent.

From the beginning of construction and till the final certificate has been issued by the consultant, defects that are discovered by inspection (patent defects) may be reported to the contractor. Then, the contractor should rectify them within a reasonable time.

However, all such defects should be rectified before the certificate of practical completion is issued.

Once practical completion has been certified, the client takes possession of the works and the defects liability period (or rectification period) begins.

If there are any defects found during the defects liability period, the client may report those to the consultant. The consultant decides whether they are in fact defects in the works (i.e. works that are not in accordance with the contract), or whether those are maintenance issues. If the consultant judges that they are defects, then the consultant may issue instructions to the contractor to rectify the defects within a reasonable time.

It is the contractor’s responsibility to identify and rectify defects, not the clients. If the client does bring any defects to the contractor’s notice, the contractor should make clear that this is not a complete list of all defects.

Examples of common latent defects include:

  • Inadequate wind posts or wall ties causing movement damage to walls.
  • Low-quality concrete or misplaced reinforcement allowing movement damage to the structure.
  • Inadequately laid foundations causing subsidence of the building.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes