Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
glass, window, cracks

Liquidated Damages

Posted on July 6, 2020January 14, 2021

Construction contracting is extremely time-sensitive. If the project gets late for completion, the client will lose anticipated revenue and profit. In addition, the client may lose opportunities for future investments. Similarly, when projects are late to complete, contractors face additional financial burdens. For example, that is maybe for employing the field and office personnel for an additional period of time.

At present, the marketplace is very competitive. No clients or contractors can afford the cost of late projects. However, in every project, there is a risk of late completion. Therefore every client tries to shift at least part of the risk onto contractors. The common form of shifting the risk is providing a liquidated damages clause in the construction agreement.

Purpose of LD

The contractor’s obligation is to complete the works by the date of completion stated in the contract. If he fails to complete the work by that date and if there is an LD clause in the contract, the contractor is liable for LD to the client. As the name implies, this is to compensate the client for financial losses or additional expenditure incurred in the event that the contractor fails to complete the works by the agreed completion date. They are not intended as a penalty. The client or the consultant has to carry out a realistic pre-assessment to determine the level of liquidated damages before the issue of the bidding documents. And the amount must be stated in the bidding documents.

The legal principle behind the liquidated damages is that damages for breach by either of the contracting party may be liquidated. But it is only up to a reasonable amount compared to the anticipated or actual loss caused by the breach. It is unreasonable to fix large liquidated damages. In addition, it is unenforceable on grounds of public policy as a penalty.

Common Definition

Liquidated Damage is a sum agreeable by the client and the contractor in advance. The contractor has to pay this amount as damages if the contractor breaches the contract by failing to complete the work on time.

LD is enforceable if the amount fixed is a genuine pre-estimate. However, it must be judged at the time the contract is entered into, of losses like to arise from the anticipated breach.

In Sri Lanka, Clause 49 of ICTAD/SBD/1 gives the provisions for liquidated damages. In Sub Clause 49.1, it says the contractor shall pay liquidated damages to the client at the rate per day stated in the Contract Data. The period is for each day that is beyond the Intended Completion Date up to the actual completion date. In addition, it says the total amount shall not exceed the amount defined in the Contract Data. The client can deduct liquidated damages from payments due to the Contractor. However, the Contractor’s liabilities shall not affect due to the payment of liquidated damages.

According to Sub Clause 49.2, if the intended completion date mentioned in the contract data is extended after liquidated damages have been paid, the consultant can correct any overpayment of liquidated damages by adjusting the next payment certificate. The Contractor shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in sub-clause 43.1.

Sample – Contract Data

(49.1) a) The liquidated damages for the whole of the Works shall be Rs: 1,000.00 per Day.

b) The maximum amount of liquidated damages for the whole of the Works shall be 10 percent of the Initial Contract Price.

Advantages of LD clause to Client

The tender document shows the amount of LD in advance. So it avoids the client having to calculate and prove the actual loss. It also concentrates the contractor’s mind on finishing the project on time.

Advantages to Contractor

In a tender situation, it fixes the contract price more certain. That is because then the Contractor can price the level of LD into his tender bid. Additionally, if the contractor thinks the project may go behind the schedule, the contractor can make a decision as to whether it would be preferable to hand the building over late and pay LD. Or else, is it worth to allocate more resources to the project and finish it on time. 

Another advantage for the contractor is the level of LD specified is a ceiling for the amount for the damages payable. The client cannot later change the amount and recover an additional sum from the contractor even the client’s actual loss is greater than the LD stated in the contract.

LD clauses and penalties

It has long been the case that if a clause for LD has been included as a penalty for late completion, rather than a genuine pre-estimate of loss, then the courts will not enforce it.  However, just because the level of LD specified in a contract is substantially higher than the loss actually suffered does not necessarily make the LD clause invalid as a penalty. 

Penalty

If the sum is “extravagant in amount in comparison with the greatest loss which could conceivably be provided to have followed from the breach”.   

To take an extreme example, if the contractor is late in completing a project, and the client can satisfy the court that the amount specified in the contract for LD was a genuine estimate of likely loss, then the LD are payable by the contractor. Practically client deducts LD from future payments due to the contractor. The client can do this even when he suffers no loss.

Genuine pre-estimate of loss

The key is that client must be able to show that the figure in the LD clause is realistic. It must be a genuine estimate of the likely loss which the client would suffer if the contractor was late in achieving practical completion. If the contractor argues about the LD amount, the Client can preferably defeat it if he can show how he arrived at the figure in question, with calculations, projections, etc. The client may take into account factors such as loss of income and increased financing costs for these calculations. As stated above, the estimate needs to reflect the position at the time of the contract. It is not at the time when the claim arises. 

LD and extensions of time

Building contracts almost invariably contain clauses entitling the contractor to an extension of the contract period in certain circumstances. For example, one reason may be the effect of exceptionally adverse weather conditions.  In such events, the client may extend the date for practical completion by an agreed period of time. Therefore, the question of LD would not arise until the expiring revised date for practical completion.

LD unenforceable

Sometimes, a court may decide that the LD clause is unenforceable. However, this does not mean that the client is then disallowed from claiming damages from the contractor for the delay. The client would merely have to rely on his common-law right to damages for breach of contract. That is for the contractor’s breach of contract for failure to complete the project on time.

Unliquidated Damages

In some contracts, the sum of liquidated money is not established in advance in the contract. In such an event, the Court determines the amount after the breach occurs. That is termed as unliquidated damages.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes