Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures
judge, hammer, judgement-1587300.jpg

Case Law – Omissions

Posted on August 28, 2021August 29, 2021

Under many standard contract conditions, there is a provision permitting the contract administrator to initiate any variation to the works. It may be in the form of an addition, modification, or omission. This provision may permit the omission of works to an unlimited degree. If so, it allows the client or his agent to omit most of the works, agreed upon originally. Then the question arises whether it is possible legally, or law places any limit on what may be omitted.

Another important matter is, although the contract provisions empower the employer or the contract administrator to omit part of the work agreed originally, it does not give the right to omit with the object of giving omitted works to another contractor. For example, the employer cannot employ another contractor to do the omitted work at a lesser rate than in the original contract.

The correct practice would be to omit only when the employer does not expect to have the omitted work done at all.

Abbey Development v PP Brickwork (2003)

The claimant, Abbey Developments Limited engaged the defendant PP Brickwork Ltd as a labour-only subcontractor for brickwork and blockwork for the development of an estate of 69 houses.

The case was initiated to clarify whether the claimant was entitled to take away the remainder of the work which the defendant had agreed to carry out. 

The claimant was invited to submit a tender by a letter of invitation dated 25th September 2000. Part of the invitation letter was as follows.

“For your information and guidance, we wish to advise the Site comprises of a total of 69 No. units and their respective Garages, and at present, it is envisaged that the construction program will last approximately 18 months.

“However, Abbey Developments Limited reserves the right to vary the number of units and the construction program without vitiating the Contract or giving rise to a claim from the sub-contractor.”

The letter of invitation further said; 

“Abbey Developments Limited reserves the right to renegotiate rates or suspend the Contract and retender the works without vitiating the Contract or giving rise to any claim from the subcontractor.”

The tender was duly submitted on 6th November. It was for a sum of £484,000. It was accompanied by a tender summary, which the tenderer had been required by the claimant to complete. The prices for each of the house types and the numbers of the prospective house types were all set out, together with those for the various types of garage. 

On 21 December 2000, the claimant sent its subcontract order to the defendant, which was accepted forming the contract.

The contract contained the usual standard provision for variations, including omissions, which would not vitiate the contract.

Some months later, after starting construction in 2001, the claimant had to write to the defendant complaining of various matters which is required to be put right. 

And then, in October, the claimant wrote to the defendant saying that it was considering determining the defendant’s contract according to clauses 6 to 13 of the General Conditions because of failure to supply sufficient labour. That drew a reply from the defendant saying there had been labour. There was an answer to that saying they were merely considering it and not going to take the matter, at that stage, any further. And these continued, further complaining about health and safety matters. Ultimately, on 12th December, the claimant wrote complaining about insufficient supervision. It was also critical of the workmanship.

Due to the above reasons, finally, the claimant terminated the contract. Part of the termination letter was as follows.

“… I am informed by our Construction Department that still you are failing to provide labour in sufficient numbers and quality to maintain our build programme.

“Therefore, we must now inform you that we are limiting your works to those plots that you currently have under construction. Following the satisfactory completion of these plots, your contract will be determined in accordance with our standard terms and conditions.

“An alternative contractor will be employed to complete the development and any additional costs to this company which result will be charged to your account.”

The additional charges of the claimant have been quantified as £8,000.

This was followed by an adjudication procedure. On 12 February 2003 the adjudicator, decided that the claimant was in repudiatory breach of contract in deciding to limit the scope of the work and that the defendant was entitled to damages of £59,727.71 plus interest and 50% of the adjudicator’s fees and expenses. He concluded that the termination letter constituted a repudiatory breach of contract by the claimant, entitling the defendant to damages.

The claimant went to the courts seeking a declaration as to whether Abbey was entitled to take away the remainder of the work which PP Brickwork had agreed to carry out. There was also an application by the defendant for the enforcement of the decision of the adjudicator which was in his favor. 

The claimant’s declarations, if granted, would mean the dispute that led to the adjudication would be resolved in favor of the claimant and the adjudicator’s decision would then be unenforceable. If the claimant were to fail in its entirety on the application, then the adjudicator’s decision would be enforceable.

The Court refused Abbey’s application, holding that under the proper construction of the subcontract, Abbey was not entitled to reduce the quantity of the works by removing all plots upon which PP Brickwork had not yet started work. The Judge determined that a convenience or omissions clause required reasonably clear words to allow an employer to transfer work from one contractor to another. The subcontract provisions allowing the variation of the quantity of work lacked clarity to allow Abbey to behave as it did. 

Accordingly, Abbey was in breach of the subcontract by engaging an alternative contractor to carry out the work which had been removed from the scope of the subcontract.

Conclusion

If a Client wants the ability to reallocate work, then the contract must be clear and specific in this regard. 

In Abbey Developments, the contract permitted the omission of work where that work was no longer required for the project. The Client sought to omit work from the contractor because he was dissatisfied with the contractor’s performance, and give this work to another contractor. The court said that reallocation was a breach of contract because the wording only provided for the omission of work in certain circumstances (where the work was no longer required).

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes