Skip to content
Menu
Civil Engineering Lectures
  • Construction Law
    • Mediation – in Construction Contracts
    • Arbitration in Construction contracts
    • Law of Contracts – Basic Legal Issues
    • DISPUTES IN CONSTRUCTION CONTRACTS
    • Law of Delict – Case Study
    • Law of Tort – An Introduction
    • Tort Law – Historical Development
    • DOCTRINE OF COMPETENCE – COMPETENCE
    • Tort Law – The parties & Vicarious Liability
    • Legal Systems in Ancient Sri Lanka
    • SECURITY OF PAYMENTS in Sri Lankan Construction Industry
    • SKILLS OF NEGOTIATIONS
    • SALE OF GOODS – IMPLIED CONDITIONS – Sri Lanka
    • Dispute resolution in Construction Projects
    • Duties, Powers, and Responsibilities of the Engineer
    • Case Law – Is it a Variation or Not?
    • Case Law – Power needed to issue variations
    • Case Law – Omissions
    • Case Law – if the Contract Administrator is not acting impartially
    • Law of contract – The Necessity of the Law
    • Law of Contract – the basics
    • Law of Contract – Unilateral and bilateral contracts
  • QUANTITY SURVEYING
    • MINIMIZING DISPUTES ARISING FROM BILL OF QUANTITIES
    • Writing Descriptions of work items in the Bill of Quantity
    • Bid Evaluation – Domestic Preference
    • Decision to tender in construction contract
    • Pre-Qualification – for Construction Contracts
    • The implication of the public procurement system to the economic growth and development of a country
    • VALUE FOR MONEY IN PROCUREMENT
    • Conditions of Contract – in Works Contracts
    • Service Contracts
    • BIDDING DOCUMENT for Works contracts
    • The Building Team
    • Methods of Tendering
    • Termination of a Construction Contract
    • Construction Claims
    • Liquidated Damages
    • BILL OF QUANTITY & THE QUANTITY SURVEYOR
    • PRELIMINARIES
    • Quantity surveyor
    • Bidding Strategy
    • Unit Rate in a Bill of Quantity
    • Price Fluctuations
    • Nominated Subcontractors
    • Building Engineering – Forces exerted on and by Buildings
    • Labor productivity – Unit rate analysis
    • Estimating Activity cost
    • Bid Price and Unbalanced Bids
    • Depreciation
    • Unit Rate Calculations – Examples – Rubble Masonry work
    • Unit rate calculation – Examples – Concrete
    • Unit rate calculation – Example – Wall painting
    • Daywork
    • Variations
    • Interim Payment Certificates
    • Contract Administration
    • ESTIMATING THE OWNING AND OPERATING COSTS OF CONSTRUCTION EQUIPMENT
  • Civil Engineering
    • MODIFICATIONS IN BUILDINGS – UNDERPINNING
    • Dewatering in Excavation
    • EXCAVATION in BUILDING CONSTRUCTION
    • The Essential Software for Civil Engineers in 2024
    • Best Software for Civil Engineering
    • PROFESSIONAL INDEMNITY INSURANCE
    • CONSTRUCTION RISKS AND INSURANCE
    • Construction machinery/equipment – Renting vs. Purchasing equipment
    • Building Engineering – An Introduction
    • ELECTRICITY – IS IT A SOURCE OF ACCIDENTS AT CONSTRUCTION SITES?
    • The Radius of Gyration (r)
    • The nature of forces acting on buildings
    • Doubly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Singly Reinforced Beams – BS 8110:1:1997 – Example 1
    • Techniques used to control groundwater
    • Glass – as construction material
    • LIME – as a construction material
    • Quality of mixing water for Concrete
    • BAILEY BRIDGE CONSTRUCTIONS
    • Waste Water Disposal
    • PROCESSES USED IN WASTEWATER TREATMENTS
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • PRELIMINARY TREATMENT OF RAW WASTEWATER
    • CONSTRUCTION MACHINERY
    • PRIMARY SEDIMENTATION TANKS
    • Biological (Secondary) Treatment Systems
    • INHERENT WEAKNESSES OF THE BUILDING INDUSTRY
    • Latent Defects and Patent Defects in Construction
    • SEGREGATION OF CONCRETE
    • CALICUT TILE ROOFING – ADVANTAGES AND DISADVANTAGES
    • Energy-Efficient Building Construction
    • DAMPNESS IN BUILDINGS
    • Septic Tank and Soakage Pit
    • Non-Load Bearing Partition Walls
    • The Versatility of Concrete
    • QUALITY MANAGEMENT IN CONSTRUCTION
    • CRYSTAL STRUCTURE OF METALS
    • SITE PRELIMINARY WORKS
    • Law of Contract – Remedies for Breach of Contract
    • INSULATION MATERIALS
    • Rubber Water stops
    • Corrosion of Reinforcing Steel: A Critical Insight
    • Bleeding Water in Concrete: Understanding and Managing Bleed Water
    • Effects of Bleeding Water on the Quality of Concrete
    • Soil Stabilization in Road Construction
    • Soil Compaction: Optimizing Soil Density for Construction
  • About us
Civil Engineering Lectures

PRIMARY SEDIMENTATION TANKS

Posted on July 4, 2024July 4, 2024

The traditional meaning of Primary treatment implies a sedimentation process to separate the readily settleable and floatable solids from the wastewater.

The treatment unit used to settle raw wastewater is termed the primary sedimentation tank (basin), primary tank (basin), or primary clarifier.

Sedimentation is the oldest and most widely used process in the successful treatment of wastewater.

After the wastewater passes the screens, comminutors, and grit chambers, the wastewater enters sedimentation tanks.

The suspended solids that are lighter than solids that fell out into the grit chamber will settle in the tank over a few hours.

The settled sludge is then removed using mechanical scrapers or pumped.

Surface skimmer devices are used to remove floatable substances on the tank surface.

Then, the effluent flows to the secondary treatment units or is discharged.

The flow velocity of wastewater in primary sedimentation tanks is reduced by plain sedimentation.

The process usually removes particles with a settling rate of 0.3 to 0.6 mm/s.

In some cases, chemicals also may be added.

Reduced suspended solids content, equalization of side stream flow, and BOD removal are the benefits of the primary sedimentation process.

The overflow rate of the primary sedimentation tanks ranges from 24.5 to 49 m3/(m2-d).

Usually, the detention time in these tanks is 1-3 hours.

Primary tanks (or primary clarifiers) remove 90-95 percent of settleable solids, 50-60 percent of total suspended solids, and 25-35 percent of the BOD5.

Type 2 flocculent settlings are the usual settling characteristics in the primary clarifier.

Due to the continuous changes in the shape, size, and specific gravity of flocculated particles, Stoke’s formula for settling velocity cannot be used to determine particle settlement.

Due to these reasons, no mathematical equation can be used to describe flocculent settling satisfactorily. Therefore, laboratory analyses such as settling-column tests are commonly used to generate design information.

RECTANGULAR BASIN DESIGN

Usually, multiple units with common walls are designed and constructed for independent operations. Basin dimensions are designed based on the surface overflow (settling) rate to calculate the required basin surface area.

The required area of the sedimentation tank is equal to the flow divided by the selected overflow rate.

An overflow rate of 36 m3/(m2•d) at average design flow is generally acceptable.

Basin surface dimensions, the length (l) to width (w) ratio (l/w), can be increased or decreased without changing the volume of the basin.

For a greater l/w ratio, the basin has a proportionally larger effective settling zone and a smaller percentage of inlet and outlet zones.

Increased basin length allows the development of a more stable flow.

The inlet structures in rectangular clarifiers are placed at one end and are designed to disperse the inlet velocity to diffuse the flow equally across the entire cross-section of the basin and to prevent short-circuiting. Typical inlets consist of small pipes with upward ells, perforated baffles, multiple ports discharging against baffles, a single pipe turned back to discharge against the headwall, simple weirs, submerged weirs sloping upward to a horizontal baffle, etc.

The inlet structure should be designed in such a way as not to trap scum or settling solids.

Baffles are installed 0.6 to 0.9 m in front of inlets to assist in diffusing the flow and submerged 0.45-0.60 m with a 5 cm water depth above the baffle to permit floating material to pass.

Scum baffles are placed in front of outlet weirs to hold back floating material from the basin effluent. These extend 15-30 cm below the water surface.

Outlets in a rectangular basin consist of weirs located toward the discharge end of the basin.

Walls of settling tanks should extend at least 150 mm above the surrounding ground surface and shall provide not less than 300 mm freeboard.

Mechanical sludge collection and withdrawal facilities are usually designed to ensure rapid removal of the settled solids.

The minimum slope of the side wall of the sludge hopper is 1.7 vertical to 1 horizontal.

The hopper bottom dimension should not exceed 600 mm.

The sludge withdrawal line is at least 150 mm in diameter and has a static head of 760 mm or greater with a velocity of 0.9 m/s.

CIRCULAR BASIN DESIGN

Inlets in circular or square basins are typically at the center and the flow is directed upward through a baffle that channels the wastewater (influent) toward the periphery of the tank.

Inlet baffles are 10-20 % of the basin diameter and extend 0.9-1.8 m below the wastewater surface.

The degree of turbulence in circular basins is higher when compared to rectangular basins. Therefore, circular basins are more efficient as flocculators.

A typical depth of the sidewall of a circular tank is 3 m.

As shown in Figure, the floor slope of the tank is typically 300 mm horizontal to 25 mm vertical.

Outlet weirs extend around the periphery of the tank with baffles extending 200-300 mm below the wastewater surface to retain floating material. Overflow weirs shall be located to optimum actual hydraulic detention time & minimize short-circuiting.

Peripheral weirs shall be placed at least 30 mm from the well.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

  • The Contract Administrator: Comprehensive Guide to the Role in Construction
  • Sustainability: Building a Better Future in Construction
  • ATTERBERG LIMITS
  • FIELD COMPACTION TESTS
  • Soil Compaction: Optimizing Soil Density for Construction

Recent Comments

  • Sembukuttige R De Silva on Soil Compaction: Optimizing Soil Density for Construction
  • Sembukuttige R De Silva on ATTERBERG LIMITS
  • Sembukuttige Rukmanthi De Silva on Sustainability: Building a Better Future in Construction
  • Sembukuttige Rukmanthi De Silva on Bid Evaluation – Domestic Preference
  • Sembukuttige Rukmanthi De Silva on Duties, Powers, and Responsibilities of the Engineer

Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING

Legal pages

  • About us
  • Contact
  • Free e-books
  • Privacy policy
  • Terms & Conditions

Lecture Categories

  • Civil Engineering
  • Construction Law
  • QUANTITY SURVEYING
©2025 Civil Engineering Lectures | Powered by SuperbThemes